Salient Features of Payra 1320MW Thermal Power Plant Project (2nd Phase)

Invitation for Bid 14.06.2018
EPC Contract Signing 16.05.2019
EPC Contractor Consortium of CECC & NEPC, China
EPC Contract Price 1.44 Billion USD
Total Project Cost 2.06 Billiion USD
Project Financer CEXIM Bank
Physical Progress 20%
Plant Capacity 1320 MW (2X660 MW)
Boiler Technology Ultra-supercritical (27 Mpa/600/610c)
Cooling Water System Closed circulation of water using cooling tower
Power Evacuation 400KV GIS Substation
Primary Fuel Imported Coal
Expected COD 1st Unit: May,2024
2nd Unit: June,2024